Article 18RKW EDF board member calls for Hinkley Point C project to be postponed

EDF board member calls for Hinkley Point C project to be postponed

by
Terry Macalister and Julia Kollewe
from Environment | The Guardian on (#18RKW)

Union-backed director says plans are 'not credible' in new blow to troubled Somerset nuclear power station development

An EDF board member has called for the 18bn Hinkley Point C nuclear power station to be postponed, in the latest sign of discord at the top of the French energy company over the troubled project.

Christian Taxil said a raft of changes to the Somerset reactor scheme agreed over the past three years significantly raised the risk for EDF, while a promise to commission the plant within 72 months of concrete being poured was "not credible".

Continue reading...

rc.img

rc.img

rc.img

a2.img
ach.imga2t.imga2t2.imgmf.gif
External Content
Source RSS or Atom Feed
Feed Location http://feeds.theguardian.com/theguardian/environment/rss
Feed Title Environment | The Guardian
Feed Link https://www.theguardian.com/us/environment
Feed Copyright Guardian News and Media Limited or its affiliated companies. All rights reserved. 2025
Reply 0 comments