COVID-19 Threatens Outages Scheduled at 97% of U.S. Nuclear Sites in 2020
The post COVID-19 Threatens Outages Scheduled at 97% of U.S. Nuclear Sites in 2020 appeared first on POWER Magazine.
Challenged by the COVID-19 pandemic, the U.S. nuclear industry has asked the Trump administration to ensure nuclear workers, suppliers, and vendors will have access to nuclear plants and personal protective equipment (PPE) during the 2020 spring and fall refueling outage seasons and beyond. All but two of the nation's nuclear sites had scheduled planned outages this year, work that the generators consider crucial to keep the lights on.
In a March 20 letter to Energy Secretary Dan Brouillette, Nuclear Energy Institute (NEI) President and CEO Maria Korsnick noted nuclear reactors have a "unique requirement" to load a fresh batch of fuel once every 18 to 24 months. The event necessitates a shut down for two to four weeks during which intense work occurs, including critical maintenance.
"Each plant typically brings in several hundred specialized workers for this work over a typical period of 30-60 days, which includes activities in advance of and following the outage. These workers typically stay in hotels or board with local families, and eat in restaurants," Korsnick wrote. In the course of performing outages and in routine operations, nuclear plant workers also use PPE and supplies for radiological protection. As the COVID-19 pandemic intensifies, the industry will also require medical PPE and supplies to minimize its spread, she said.
Asked on March 26 whether the Trump administration has responded, and any immediate action can be anticipated, the NEI told POWER: "We continue to work with the Administration to address how best to support the industry and our workforce during this time. We know that nuclear power plant operation and continued electricity is critical to powering our hospitals and keeping the lights on in our homes and emergency centers."
Planned Nuclear Refueling Outages in 2020As the EIA notes, the U.S. has 58 commercially operating nuclear power plants with 96 nuclear reactors in 29 U.S. states. Of these nuclear plants, 32 plants have two reactors and 3 plants have three reactors. In 2020, some reactors at 56 of the nation's 58 nuclear sites in 21 states-including several that have issued lockdown measures-planned to undergo refueling outages. At least 31 of the 58 sites had scheduled outages between mid-February and early May. The remaining 25 planned refueling outages between late August and late October.
The average U.S. refueling outage times have shortened in recent years-decreasing from an average of 46 days in 2012 to 32 days in 2019-owing in part to improved and planning and execution practices for refueling outages over the years, NEI told POWER. Of significant note is that the 2020 season is poised to be especially busy in part because planned nuclear generation outages are generally timed to coincide with a plant's refueling cycle, it said.
Table. Expected U.S. Nuclear Plant Refueling Outages in 2020. Courtesy: NEI
Plant | City | State | Company | Approx. Start | |
1 | Browns Ferry | Athens | AL | Tennessee Valley Authority | Mid February |
2 | Grand Gulf | Port Gibson | MS | Entergy | Mid February |
3 | Brunswick | Southport | NC | Duke Energy Progress | late February |
4 | Davis Besse | Oak Harbor | OH | First Energy | Late February |
5 | Byron | Byron | IL | Exelon | Early March |
6 | Nine Mile | Oswego | NY | Exelon | Early March |
7 | Vogtle | Augusta | GA | Southern Nuclear Operating Co. | Early March |
8 | South Texas Project | Wadsworth | TX | STP Nuclear Operating Co. | Early March |
9 | Arkansas Nuclear One | Russellville | AR | Entergy | Early March |
10 | Point Beach | Two Rivers | WI | NextEra (FPL) | Early March |
11 | Salem | Hancocks Bridge | NJ | PSEG | Early March |
12 | Fermi | Frenchtown Charter Twp. | MI | DTE Energy | Mid March |
13 | McGuire | Huntersville | NC | Duke Energy | Mid March |
14 | Susquehanna | Berwick | PA | Talen Energy | Mid March |
15 | Sequoyah | Soddy Daisy | TN | Tennessee Valley Authority | Late March |
16 | Beaver Valley | Shippingport | PA | FirstEnergy | Late March |
17 | Limerick | Pottstown | PA | Exelon | Late March |
18 | Quad Cities | Cordova | IL | Exelon | Late March |
19 | Turkey Point | Florida City | FL | Florida Power & Light | Late March |
20 | Seabrook | Seabrook | NH | NextEra Energy | Early April |
21 | Salem | Hancocks Bridge | NJ | PSEG | Early April |
22 | Palo Verde | Tonopah | AZ | Arizona Public Service Company | Early April |
23 | Comanche Peak | Glen Rose | TX | Luminant | Early April |
24 | Ginna | Ontario | NY | Exelon | Early April |
25 | Oconee | Seneca | SC | Duke Energy | Early April |
26 | VC Summer | Jenkinsville | SC | Dominion Energy | Early April |
27 | Millstone | Waterford | CT | Dominion Energy | Early April |
28 | Braidwood | Braceville | IL | Exelon | Mid April |
29 | Watts Bar | Spring City | TN | Tennessee Valley Authority | Mid April |
30 | Catawba | York | SC | Duke Energy | Early May |
31 | Surry | Surry | VA | Dominion Energy | Early May |
32 | Indian Point | Buchanan | NY | Entergy | Early May |
33 | Palisades | Covert | MI | Entergy | Late August |
34 | North Anna | Mineral | VA | Dominion Energy | Early September |
35 | Robinson | Hartsville | SC | Duke Energy Progress | Early September |
36 | Vogtle | Augusta | GA | Southern Nuclear Operating Co. | Early September |
37 | Fitzpatrick | Oswego | NY | Exelon | Early September |
38 | Prairie Island | Welch | MN | Northern States Power | Early September |
39 | DC Cook | Bridgman | MI | AEP | Mid September |
40 | McGuire | Huntersville | NC | Duke Energy | Mid September |
41 | Cooper | Brownville | NE | Nebraska Public Power District | Mid September |
42 | Waterford | Killona | LA | Entergy | Mid September |
43 | Point Beach | Two Rivers | WI | NextEra (FPL) | Early October |
44 | Salem | Hancocks Bridge | NJ | PSEG | Early October |
45 | Palo Verde | Tonopah | AZ | Arizona Public Service Company | Early October |
46 | Browns Ferry | Athens | AL | Tennessee Valley Authority | Early October |
47 | Diablo Canyon | Avila Beach | CA | Pacific Gas & Electric | Early October |
48 | Callaway | Fulton | MO | Ameren | Early October |
49 | Byron | Byron | IL | Exelon | Early October |
50 | Turkey Point | Florida City | FL | Florida Power & Light | Early October |
51 | Farley | Dothan | AL | Southern Nuclear Operating Co. | Early October |
52 | Comanche Peak | Glen Rose | TX | Luminant | Early October |
53 | Peach Bottom | Delta | PA | Exelon | Mid October |
54 | Millstone | Waterford | CT | Dominion Energy | Mid October |
55 | Watts Bar | Spring City | TN | Tennessee Valley Authority | Mid October |
56 | Duane Arnold | Palo | IA | NextEra Energy | Late October |
As of March 25, according to the Nuclear Regulatory Commission (NRC), 13 of the U.S.'s 96 commercial nuclear reactors were offline for refueling outages: Indian Point 3, Nine Mile Point 1, Susquehanna 2, Browns Ferry 2, Brunswick 2, McGuire 1, North Anna 2, Turkey Point 4, Vogtle 2, D.C. Cook 1, Perry 1, Point Beach 1, and Quad Cities 1. At least five others were coasting down in preparation for refueling outages: Limerick 2, Salem 1, Byron 2, Monticello, and Comanche Peak 1.
The Energy Information Administration (EIA), which compiles data from the NRC into a useful interactive map that shows the status of U.S. nuclear outages, noted that 16.9% of total U.S. nuclear capacity-about 17 GW of the total 100 GW-was offline as of March 25.
The Energy Information Administration (EIA) provides a useful interactive graphic that shows the current and historic status of U.S. nuclear capacity and outages. This graphic is from March 25, as the industry prepared for several refueling outages scheduled for this spring. According to this data, nuclear plants that were in full outage mode are: Grand Gulf in Mississippi, Fermi in Michigan, and Davis Besse in Ohio, while Harris in North Carolina was operating at only 8%. Source: EIAA Compounding CrisisThe NEI said that across the nuclear fleet precautions are being taken to limit the risks of COVID-19. Among the actions are:
- Directing employees who don't feel well to stay home, encouraging them to seek medical attention, and asking for a report on their condition;
- Excluding personnel who have recently been in countries impacted by the virus;
- Screening of employees, contractors, and any necessary visitors at the plant gate and, at some
plants, taking their temperature; - Disinfecting surfaces more often;
- Closing or limiting access to cafeterias and other places employees congregate; and
- Increasing the number of hand-washing facilities.
Because refueling outages are so critical to the safe and reliable operations of nuclear power plants, the Trump administration should consider several actions that would immediately benefit nuclear owners, operators, and vendors, Korsnick said.
For one, she urged Brouillette to ensure that federal designation of essential workers include workers that support nuclear operations. The Trump administration's March 19-issued initial list of "essential critical infrastructure workers" broadly includes "workers needed for safe and secure operations at nuclear generation," but it does not specify whether the extensive list of specialized contract workers needed for outage work are qualified.
Korsnick also urged the administration to allow "unfettered" travel to plants for the performance of essential outage activities. Noting that the workforce is sometimes sourced abroad, she also asked it to "permit international workers who perform highly specialized functions to travel into the U.S. and establish protocols immediately to enable their safe entry."
To accommodate workers, she also urged the administration to keep open hotel and food services. Finally, she asked for priority for PPE, specifically asking for surgeons' gloves, sanitized wipes, dust masks, and disposable thermometers-as well as COVID-19 testing kits, and necessary radiological and medical protective equipment and supplies for nuclear workers.
At Exelon Generation-which embarked on refueling outages at Byron 1 on March 9, Nine Mile Point 2 on March 5, Calvert Cliffs 1 on Feb. 17, and LaSalle 1 on Feb. 10-work appears to continue as scheduled. "Exelon Generation's highly trained nuclear employees and skilled contractors understand the critical role that Exelon Generation's nuclear facilities play in powering hospitals, regional response centers and millions of homes and essential businesses during the COVID-19 pandemic-and they are prepared to meet the challenge," the company told POWER on March 26.
The work is crucial because the company's nuclear facilities run at full power more than 95% of the time and its fixed fuel contracts allow it to operate a unit between 18 months and two years without stopping to refuel, it explained.
At Byron 1 in Illinois, more than 1,200 supplemental workers joined the 800 Exelon Generation employees in prepping the facility for another reliable run, the company said. Workers arrived several weeks before the outage and some will remain when it is complete. At Nine Mile 1 in New York, 1,300 workers arrived onsite "from outside the area." About 1,000 additional workers were onsite at Calvert Cliffs 1 in Maryland, and another 1,000 workers went to LaSalle 1 southwest of Chicago.
"We are closely following CDC guidance at all our generating facilities to prevent the spread of germs and viruses. We are also limiting travel; minimizing personal contact; encouraging remote-enabled employees to work from home, encouraging frequent hand washing and scheduling additional facility cleanings," Exelon said.
However, it is also working to ensure employees and contractors supporting the projects "are subject to additional precautions due to the number of people required to support refueling outage and maintenance activities."
Exelon said that prior to entry, "each person must complete a rigorous self-screening for signs of fever or respiratory issues before reporting to work. Any employees and contractors that experience any flu-like symptoms, are being instructed not to enter our facilities and to seek offsite medical evaluation. We also have medical professionals staffing our outage facilities around-the-clock to closely monitor employee health."
Sourcing outage workers, which can pose a challenge even during ordinary outage seasons, has this year especially benefitted from employee determination, the company suggested. "Our employees understand the importance of providing reliable, baseload, carbon-free energy to the community, and are rallying to support our stations and take additional precautions to protect themselves, along with their coworkers, families and communities." Exelon, meanwhile, is doing all it can to ensure work goes on, underscoring its role as a provider of critical resources. "We have robust plans and contingencies to ensure business continuity," it said.
-Sonal Patelis a POWER senior associate editor (@sonalcpatel,@POWERmagazine).
Updated (March 27): Adds comments from NEI and Exelon Generation.
Clarification (March 30): Work is scheduled at 56 of the 58 nuclear sites in the U.S., not 97% of the total nuclear fleet. This is an important clarification because there are 58 commercially operating nuclear power plants with 96 nuclear reactors in 29 U.S. states. Of these nuclear plants, 32 plants have two reactors and 3 plants have three reactors. To reflect this clarification, the headline changes "plants" to "sites."
The post COVID-19 Threatens Outages Scheduled at 97% of U.S. Nuclear Sites in 2020 appeared first on POWER Magazine.