Article 6TJ0F Sizewell C cost ‘has doubled since 2020 and could near £40bn’

Sizewell C cost ‘has doubled since 2020 and could near £40bn’

by
Jillian Ambrose
from Environment | The Guardian on (#6TJ0F)

Treasury expected to decide whether to support EDF-backed nuclear power plant in this year's spending review

The cost of building the Sizewell C nuclear power plant in Suffolk has doubled since the plans were presented to the UK government in 2020 and could now reach close to 40bn, according to reports.

A rise in construction charges over recent years, combined with cost overruns and delays at EDF's Hinkley Point C nuclear project in Somerset is expected to increase the final bill to build a successor project at Sizewell, according to the Financial Times.

Continue reading...
External Content
Source RSS or Atom Feed
Feed Location http://feeds.theguardian.com/theguardian/environment/rss
Feed Title Environment | The Guardian
Feed Link https://www.theguardian.com/us/environment
Feed Copyright Guardian News and Media Limited or its affiliated companies. All rights reserved. 2025
Reply 0 comments