Article 6Y5QP Power utility built $95 million 500-megawatt power substation for Intel's $100 billion Ohio fab, but six-year delay leaves substation capable of powering 500,000 homes idle

Power utility built $95 million 500-megawatt power substation for Intel's $100 billion Ohio fab, but six-year delay leaves substation capable of powering 500,000 homes idle

by
ashilov@gmail.com (Anton Shilov)
from Latest from Tom's Hardware on (#6Y5QP)
Intel has once again postponed the launch of its Ohio chip plant, which is now expected in 2031, leaving utility AEP Ohio with an idle $95 million substation.