Snowy Hydro 2.0 flags another cost blowout with $12bn price tag now considered unachievable
by Tom McIlroy Political editor from on (#70G1M)
Pumped hydro project in Kosciuszko national park is 67% complete, but supply chain cost increases and issues with a borer have caused cost overrun
Get our breaking news email, free app or daily news podcast
Snowy Hydro is preparing for another significant cost overrun on the massive Snowy 2.0 project in the Kosciuszko national park, with a line-by-line reassessment ordered from contractors on Friday.
The giant pumped hydro project, first touted by the Turnbull government in 2017 as costing $2bn, was later revised to a cost of $5.9bn. Escalating to almost $13bn in 2023, construction is due to be completed by the end of 2028.