Article 79EX7 National Grid to site biggest substation in UK near planned Teesside datacentre

National Grid to site biggest substation in UK near planned Teesside datacentre

by
Lauren Almeida
from Technology | The Guardian on (#79EX7)

New electricity generating capacity would enable north-east to attract investment for large-scale AI infrastructure

National Grid has taken a step towards building Britain's biggest electricity substation on Teesside, which could supply power to a vast neighbouring datacentre as the UK races to expand its AI infrastructure.

Last week, the company agreed to purchase 29.5 hectares (73 acres) of land at Dorman Point on a site owned by Teesworks, a local private-public partnership. The deal was first reported by Sky News.

Continue reading...
External Content
Source RSS or Atom Feed
Feed Location http://www.theguardian.com/technology/rss
Feed Title Technology | The Guardian
Feed Link https://www.theguardian.com/us/technology
Feed Copyright Guardian News and Media Limited or its affiliated companies. All rights reserved. 2026
Reply 0 comments