County will create temporary bike lane during U Bridge trolley wire work
From a King County Metro construction notice (PDF).King County Metro is starting work on a months-long project to replace some trolley wire poles on the University Bridge that will displace the current bike lane in places. The agency will create a temporary bike lane around the work zone that is protected from traffic by movable water-filled barriers. The street will be reduced to one general traffic lane near work zones.
Work is expected to be complete in spring 2027. Crews will do the west (southbound) side of the street first, then shift to the east side. Other power line work will be needed in the area to support the work.
It is great to see a proper bike detour from King County, and it seems well-considered if the plan outlined in the construction notice is followed at all times. The U Bridge is the only bridge over the Ship Canal with dedicated bike lanes, and it is not safe for people on bikes to detour into the general purpose lanes due to the slippery metal grating on the moving bascule section. Access to the bike lanes is vital.
This is also a good time for construction detours on the bridge since construction work for the RapidRide J line has already heavily disrupted this bike route on Roosevelt Way, 11th Ave NE and Eastlake Ave. Sections of bike lane have been closed for months, often requiring people to choose between busy mixed traffic lanes or very skinny sidewalks.
Hopefully SDOT and King County Metro can work together to upgrade the plastic posts lining the bike lane, which were mostly destroyed and in need of replacement even before work began. The bridge needs something more robust than plastic flex posts alone, which have been replaced several times over the years and do not last long. Adding barriers to bridge structures is often more complicated than it might seem since weight and bridge deck design and condition affect the options.