Belo Monte dam operations delayed by Brazil court ruling on indigenous people
by Jonathan Watts from on (#10TTG)
World's fourth largest hydropower plant's license was suspended weeks before testing turbines because operators failed to compensate local communities
The start of operations at Brazil's Belo Monte dam could be held up following a court judgment that operators have yet to provide adequate support to indigenous groups affected by the giant construction.
Related: Belo Monte, Brazil: The tribes living in the shadow of a megadam
Continue reading...