Benefits of High-Voltage Direct Current Transmission Systems
High-voltage direct current (HVDC) technology offers several advantages compared to alternating current transmission systems. For example, it allows more efficient bulk power transfer over long distances. However, cost is an important variable in the equation. Once installed, HVDC transmission systems are an integral part of the electrical power system, improving stability, reliability, and transmission capacity.
Typical utility-scale power plants generate alternating current (AC) electricity, and most electrical loads run on AC power. Thus, the majority of transmission lines carrying power around the world are of the AC type. However, there are instances when high-voltage direct current (HVDC) transmission systems offer significant benefits.
"One big advantage to HVDC is the efficiency of power transmission over long distances," George Culbertson, vice president of power delivery markets for HDR, told POWER. "If the transmission line route is longer than about 300 miles, DC is a better option because AC lines have more line losses than DC for bulk power transfer."
Converting from AC to DCThe challenge, however, is that to transmit via HVDC, two converter stations are needed. First, the AC power must be converted to DC to begin the transmission process, and then when it gets to the desired tie-in destination, the DC power must be converted back to AC to be utilized on the grid.
Conversion technology is well-established. Electrical pioneers were working on the building blocks for HVDC-links back in the late 1800s. Conventional HVDC converter technology is based on the use of line-commutated or phase-commutated converters. In 1954, ASEA, the predecessor of ABB, used this classic technology utilizing mercury arc valves to construct the world's first commercial HVDC link between Vistervik, on the east coast of Sweden, and Ygne, on the island of Gotland in the Baltic Sea. The original Gotland link could transfer 20 MW over a 98-kilometer (km)-long submarine cable with a voltage of 100 kV. The service was re-engineered in 1970, increasing capacity to 30 MW at a voltage of 150 kV through the addition of a thyristor valve bridge.
ASEA continued to push boundaries, developing new HVDC systems during the decades that followed. In 1997, ABB commissioned the world's first HVDC demonstration project using voltage source converters (VSCs). VSC technology uses gate turn-off switching devices, such as insulated-gate bipolar transistors (IGBTs), to perform the conversion. An IGBTs high switching frequency capability allows more-precise VSC control and less-complex circuit configuration through the use of pulse width modulation techniques. ABB named its new VSC-based product HVDC Light.
VSC technology was further improved when Siemens introduced a modular multilevel converter (MMC). The Trans Bay Cable project, which runs between San Francisco and Pittsburg, California, was completed in 2010, using Siemens' HVDC Plus system. MMC technology offers excellent harmonic performance and reduced power losses compared to previous VSCs. All HVDC manufacturers are applying MMC technology in VSCs today.
Platform to ShoreVince Curci, underground transmission project manager with HDR, said one of the advantages of VSC technology is that it is very compact. "They require maybe 30% of the area of a conventional converter and about 50% of the weight," Curci said. That makes them a good choice for offshore wind farms. "A 600-MW VSC requires less than one acre of land, whereas a conventional converter requires three or four acres. So, the advantage of this new technology is that you can put them at sea on a small footprint and transfer power to land via submarine cables."
One example of that is the DolWin2 project (Figure 1). TenneT, a European transmission system operator with operations in the Netherlands and Germany, required a 916-MW HVDC link to connect the Nordsee One, Gode Wind I, and Gode Wind II wind farms to the onshore transmission grid. ABB designed, supplied, installed, and commissioned the compact offshore and onshore converter stations, as well as the subsea and underground cable systems.
1. Offshore link. DolWin2-completed in 2017-ties three North Sea wind farms to the German power grid via a 916-MW high-voltage direct current (HVDC) transmission link. Courtesy: ABB |
The wind farms are connected with AC cables to an HVDC converter station installed on an offshore platform in the North Sea. The DC power is then transmitted through a 45-km-long sea-cable system (Figure 2) and further 90-km-long land cable to an onshore HVDC station at the grid connection point of Dirpen West. The project was completed by ABB and handed over to TenneT in June 2017.
2. Subsea cables. Power generated by the Nordsee One, Gode Wind I, and Gode Wind II offshore wind farms is transmitted to land via HVDC subsea cables, shown here during installation. Courtesy: TenneT |
"HVDC is the technology of choice for reliably and efficiently transmitting large amounts of power over long distances with minimal losses. It is ideal for integrating remote renewable energy into the power grid," Claudio Facchin, president of ABB's Power Grids division, said in a press release announcing the project's completion. Siemens has also completed projects of this nature.
Analyzing OptionsOne thing that often puts the kibosh on an HVDC project is cost. Converter stations are expensive. "VSCs for a large HVDC transmission project could cost in excess of $100 million and depends on voltage and power rating," Curci said. Therefore, it's prudent to complete a study of the available alternatives. Three main factors need to be considered.
"It depends on the distance, it depends on the voltage, and it depends on the power transfer," Curci said. "There are typically breakeven studies done, which include lifecycle cost, and then you reach a point where the HVDC system becomes more economical based on these factors.
"AC systems have lower capital costs, but a much steeper line slope as you increase the distance. Along the length, they need compensation, especially at high voltages, because they require what we call VAR [volt-ampere reactive] support," continued Curci. "HVDC systems have a much higher capital cost, but as the distance increases the slope of the line is flatter. So, there is a point where these two lines intersect, and that's your breakeven point-that's a function of distance, voltage, and power transfer."
Culbertson recalled a study he had been involved with early in his career. It was completed for a gas company that was trying to determine if it was more cost-effective to build a natural gas pipeline or an HVDC transmission line from Turkmenistan, where gas was plentiful, to Pakistan, where power was needed, by way of Afghanistan. Both options were very expensive. Ultimately, the project never got off the ground due in large part to political unrest in the region.
But there are plenty of projects that are moving forward. In March 2017, a consortium between Siemens and Sumitomo Electric Industries Ltd. was awarded an HVDC order from Indian transmission operator Power Grid Corp. of India. The team will construct a 200-km-long HVDC connection, using both underground cable and overhead lines, between Pugalur, Tamil Nadu, and Trichur, Kerala. It will be India's first HVDC link featuring VSC technology. Siemens is supplying two converter stations with two 1,000-MW parallel converters, while Sumitomo Electric is responsible for the cross-linked polyethylene HVDC cable system in the DC circuit. The combined order volume for the two companies is about $520 million. Grid connection is scheduled in the first half of 2020.
Siemens is also involved in a couple of UK projects. The Nemo Link will interconnect the British and Belgian national grids via subsea cable. Siemens is responsible for the turnkey installation of a converter station on an 8-hectare site in southeast England, formerly occupied by the Richborough Power Station, and a similar converter station in the Herdersbrug industry zone in Bruges, Belgium. The 140-km-long link, with a 1,000-MW capacity and 400-kV operating voltage, is expected to enter commercial operation in 2019. Additionally, the ElecLink will connect the British and French power grids. HVDC cables will be routed through the Channel Tunnel as part of that project. The 51-km-long link will have a 1,000-MW capacity and 320-kV operating voltage (Figure 3).
ABB is also working on a project that will connect the English and French markets. With a capacity of 1,000-MW, the link will run from Chilling, Hampshire, on the southern coast of England, to Tourbe in northern France-a distance of 240 km across the English Channel. Furthermore, ABB received an order in early July to upgrade the HVDC link that interconnects New Zealand's north and south islands.
Permitting and Cost"From my perspective, one of the biggest challenges to any project is permitting, especially when you're talking about a 500- or 1,000-mile line," said Culbertson. "You're going to be crossing different jurisdictions-cities, counties, states, or even countries."
However, that challenge isn't isolated to HVDC projects. Any transmission project can face difficulty obtaining the necessary permits. There is often a negative public reaction from impacted residents who don't want to see towers running through their neighborhoods or across their land. In the western U.S., there is a lot of federal land that may need to be crossed, which adds complexity with respect to obtaining permits from agencies such as the Bureau of Land Management.
Almost all projects require some form of environmental impact study to address temporary and permanent impacts, and the process can be time-consuming, sometimes requiring years to complete. Furthermore, there are right-of-way requirements that must be adhered to in terms of width for installation, operation, and maintenance, depending on voltage and number of lines. There are also horizontal and vertical clearance obligations-really nothing is left to chance.
Although converter stations are expensive, HVDC projects do have some cost advantages over AC systems. "DC lines can actually be cheaper per mile because of the way the conductors are configured," said Culbertson. "You have to have three separate phases for AC, so for a large line you have three sets of conductors, usually they're multiple bundles of conductor-very heavy-and the towers have to be pretty massive to hold all that weight. That additional steel and aluminum also adds to the visual impact.
"A DC line can deliver comparable amounts-or even higher amounts-of power using only two sets of conductors as opposed to three, so the towers don't have to be quite as large resulting in much less installed cost on the transmission part of it. You can also run longer DC lines underground. So, there can be a big advantage to DC where permitting and visual impact is a concern," Culbertson said. a-
-Aaron Larsonis POWER's executive editor.
The post Benefits of High-Voltage Direct Current Transmission Systems appeared first on POWER Magazine.