Article 5SGYA Energy firms fined after subsea cable delay pauses Scottish windfarms

Energy firms fined after subsea cable delay pauses Scottish windfarms

by
Jillian Ambrose Energy correspondent
from Environment | The Guardian on (#5SGYA)

Turbine sites paid to switch off on windy days because there was no way to transmit power to south of UK

Two energy companies will pay a record 158m fine after delays to a major subsea power cable bringing renewable energy from Scotland to England and Wales caused home energy bills to rise.

National Grid and Scottish Power agreed to pay the penalty after an investigation by the industry regulator found many of Scotland's windfarms were paid to turn off on windy days because there was no way to transmit the clean electricity to areas of high energy demand in the south of the UK.

Continue reading...
External Content
Source RSS or Atom Feed
Feed Location http://feeds.theguardian.com/theguardian/environment/rss
Feed Title Environment | The Guardian
Feed Link https://www.theguardian.com/us/environment
Feed Copyright Guardian News and Media Limited or its affiliated companies. All rights reserved. 2024
Reply 0 comments