NSW renewable energy zones up to two years behind schedule
by Peter Hannam from on (#6BWNG)
We are not going to allow the lights to go off,' state energy minister Penny Sharpe vows
- Follow our Australia news live blog for the latest updates
- Get our morning and afternoon news emails, free app or daily news podcast
New South Wales' two main renewable energy zones will be delayed for as long as two years and cost more to build with landholder opposition to new transmission lines partly to blame, the energy minister, Penny Sharpe, has said.
The Minns government briefed journalists about its network infrastructure strategy on Wednesday, revealing that the central-west Orana zone would not hit its energisation date" until 2027-28, compared with an initial 2025 target. Similarly, the New England zone will now start in 2029 compared with an initial 2027 goal.
Continue reading...