Article 6EASQ Snowy Hydro 2.0 costs blowout confirmed to be almost $13bn

Snowy Hydro 2.0 costs blowout confirmed to be almost $13bn

by
Peter Hannam
from World news | The Guardian on (#6EASQ)

The revised estimate for the scheme is contingent on completion by end of 2028 and may rise further if delays persist

Snowy Hydro's two main energy projects have had their completion costs double to almost $13bn as delays and rising costs for equipment and staff take their toll.

The giant Snowy 2.0 pumped hydro project in the Kosciuszko national park, first touted by the Turnbull government in 2017 as costing $2bn, was later revised to a cost of $5.9bn. That tally, though, has escalated to $12bn, with that estimate contingent on completion by the end of 2028.

Sign up for Guardian Australia's free morning and afternoon email newsletters for your daily news roundup

Continue reading...
External Content
Source RSS or Atom Feed
Feed Location http://feeds.theguardian.com/theguardian/world/rss
Feed Title World news | The Guardian
Feed Link https://www.theguardian.com/world
Feed Copyright Guardian News and Media Limited or its affiliated companies. All rights reserved. 2024
Reply 0 comments