Article 6EAZW Chris Minns rules out underground power lines for controversial HumeLink project due to cost

Chris Minns rules out underground power lines for controversial HumeLink project due to cost

by
Cait Kelly
from Environment | The Guardian on (#6EAZW)

Parliamentary committee recommends overhead transmission but groups opposing 360km of lines being built across regional NSW vow to keep fighting

Premier Chris Minns has poured cold water on the potential of undergrounding" the transmission line project that will be built across regional New South Wales to connect renewable energy zones and carry clean energy across the country.

The controversial HumeLink project is vital to the country's energy transmission, with the Australian Energy Market Operator estimating Australia needs more than 10,000km of new transmission lines and a ninefold increase in large-scale wind and solar energy.

Sign up for Guardian Australia's free morning and afternoon email newsletters for your daily news roundup

Continue reading...
External Content
Source RSS or Atom Feed
Feed Location http://feeds.theguardian.com/theguardian/environment/rss
Feed Title Environment | The Guardian
Feed Link https://www.theguardian.com/us/environment
Feed Copyright Guardian News and Media Limited or its affiliated companies. All rights reserved. 2024
Reply 0 comments