Article 6TXZZ Hinkley Point C owner warns fish protection row may further delay nuclear plant

Hinkley Point C owner warns fish protection row may further delay nuclear plant

by
Jillian Ambrose
from on (#6TXZZ)

Solution to stop River Severn fish being sucked into cooling systems taking too long to resolve, EDF says

The owner of Hinkley Point C in Somerset has warned that the much-delayed construction of Britain's first new nuclear power plant in a generation could face further hold-ups because of a row over its impact on local fish.

The nuclear developer, EDF Energy, warned that the lengthy process" to agree to a solution with local communities to protect fish in the River Severn had the potential to delay the operation of the power station".

Continue reading...