GE Vernova Completes Turbine Upgrades at InterGen Gas-Fired Plant in the UK
GE Vernova said the energy giant has completed a modernization project at InterGen's 800MW Coryton Power Plant in the UK. The group on February 9 said the work included two high-efficiency (HE) upgrades on GT26 gas turbines, delivering 85 MW of additional generation capacity, a 2.46% efficiency gain.The post GE Vernova Completes Turbine Upgrades at InterGen Gas-Fired Plant in the UK appeared first on POWER Magazine.