V.C. Summer Expansion Project 64.1 Percent Complete
Progress at the V.C. Summer expansion project has reached 64.1 percent, SCE&G's latest report to the South Carolina Public Service Commission shows. The figure takes into account various phases, including engineering - now considered 96 percent complete - procurement at 88.2 percent complete, construction at 34.3 percent complete and start up activities, which are considered 8.6 percent complete.(read more)