Article 2NS28 V.C. Summer Expansion Project 64.1 Percent Complete

V.C. Summer Expansion Project 64.1 Percent Complete

by
Nuclear Street News
from News on (#2NS28)
Progress at the V.C. Summer expansion project has reached 64.1 percent, SCE&G's latest report to the South Carolina Public Service Commission shows. The figure takes into account various phases, including engineering - now considered 96 percent complete - procurement at 88.2 percent complete, construction at 34.3 percent complete and start up activities, which are considered 8.6 percent complete.(read more)aggbug?PostID=43513&AppID=34&AppType=Web
External Content
Source RSS or Atom Feed
Feed Location http://nuclearstreet.com/nuclear_power_industry_news/b/nuclear_power_news/rss.aspx
Feed Title News
Feed Link https://nuclearstreet.com/nuclear_power_industry_news/b/nuclear_power_news
Reply 0 comments