Article 40J0Q There’s a new report on SLS rocket management, and it’s pretty brutal

There’s a new report on SLS rocket management, and it’s pretty brutal

by
Eric Berger
from Ars Technica - All content on (#40J0Q)
12678324214_e83189ae74_b-800x450.jpg

Enlarge / This artist rendering shows an aerial view of the liftoff of the SLS rocket during Exploration Mission 1. (credit: NASA)

Boeing has been building the core stage of NASA's Space Launch System rocket for the better part of this decade, and the process has not always gone smoothly, with significant overruns and multiyear delays. A new report from NASA's inspector general makes clear just how badly the development process has gone, laying the blame mostly at the feet of Boeing.

"We found Boeing's poor performance is the main reason for the significant cost increases and schedule delays to developing the SLS core stage," the report, signed by NASA Inspector General Paul Martin, states. "Specifically, the project's cost and schedule issues stem primarily from management, technical, and infrastructure issues directly related to Boeing's performance."

As of August 2018, the report says, NASA has spent a total of $11.9 billion on the SLS. Even so, the rocket's critical core stage will be delivered more than three years later than initially planned-at double the anticipated cost. Overall, there are a number of top-line findings in this report, which cast a mostly if not completely negative light on Boeing and, to a lesser extent, NASA and its most expensive spaceflight project.

Read 14 remaining paragraphs | Comments

index?i=j2gYN8LQY8o:myTlIkhmWHI:V_sGLiPB index?i=j2gYN8LQY8o:myTlIkhmWHI:F7zBnMyn index?d=qj6IDK7rITs index?d=yIl2AUoC8zA
External Content
Source RSS or Atom Feed
Feed Location http://feeds.arstechnica.com/arstechnica/index
Feed Title Ars Technica - All content
Feed Link https://arstechnica.com/
Reply 0 comments