Article 6KZSX A sneak peek at the 2 Line’s South Bellevue Station

A sneak peek at the 2 Line’s South Bellevue Station

by
Sherwin Lee
from Seattle Transit Blog on (#6KZSX)

Yesterday, I had the chance to join members of the press in a media tour of South Bellevue Station, which will open for Link operations in just a matter of weeks when the East Link Starter Line begins service. As things currently stand, the ELSL will open to the public on April 27th, while the full extension across I-90 is still tentatively set for 2025.

At South Bellevue, the accompanying park-and-ride garage has been open for more than two years and the station itself has been finished for quite for time. However, only recently was tile replacement completed on the platform, which was necessary after quality issues surfaced during the initial installation. According to Jon Lebo, East Link Executive Director, Sound Transit placed full-time inspectors over the replacement work to avoid repeat mistakes.

Operationally, the ELSL has been undergoing pre-revenue testing at the scheduled headways of 10 minutes. Lebo indicated that operator staffing is already at desired levels, with well over 100 operators hired specifically to drive ELSL trains. When the line opens, two-car train service is expected to serve roughly 6,000 daily boardings.

IMG_3101.jpg?resize=525%2C394&ssl=1

Matt Sheldon, Deputy Executive Director of Planning & Integration, also gave some additional insight into the system-wide service impacts that are anticipated. No immediate service changes are planned for the ELSL opening but once the full cross-lake 2 Line opens, the 550 will be completely replaced, with its Bellevue Way market covered by the rerouted 554. Mike has previously written about the broader suite of changes.

According to Sheldon, Sound Transit is also continuing to look at paid parking options across the system, but the Board hasn't given direction about specific locations to target. I asked if the agency had looked at updated park-and-ride utilization forecasts, given that many park-and-rides are much barer than they were pre-COVID. Sheldon indicated that no new forecasts have been done (Metro has not updated their publicly-available reports since 2017), but was optimistic that the ELSL will create new ridership markets and that South Bellevue Station parking will gradually fill in over time.

External Content
Source RSS or Atom Feed
Feed Location https://feeds.feedburner.com/seattletransitblog/rss
Feed Title Seattle Transit Blog
Feed Link https://seattletransitblog.com/
Reply 0 comments