Story ImageAnd up to 70% of stalled energy generation projects are unlikely to be approved, claims regulator Ofgem

While the UK government wants to turbocharge datacenter construction, a newly published report says there are already 400 GW worth of outstanding requests for connection to the power grid around London, and regulator Ofgem estimates 60-70 percent of these will never happen....