2028-2030 To Get a GE 290-430MW Natural Gas Turbine
by Brian Wang from NextBigFuture.com on (#708JP)
A new order for a GE Vernova 7HA gas turbine placed today would likely see delivery in late 2028 at the earliest, with potential delays extending to 2029-2030 depending on production ramp-up and order prioritization. This equates to a lead time of approximately 3-4 years from order date, though some reports indicate quotes up to ...