NASA auditors warned Thursday the space agency faces "significant safety and technical challenges" that need to be solved before astronauts fly in private capsules.
In its report, NASA's inspector general office noted Boeing and SpaceX are several years late in transporting crews to the International Space Station. The private capsules likely won't be certified before next summer, according to the report, and NASA should set a realistic timetable to avoid compromising safety.
NASA officials concurred with this and most of the other recommendations in the 53-page audit.
The auditors reported, meanwhile, that NASA overpaid Boeing $287.2 million to keep the company moving forward. Most of this overcharge was unnecessary, they said, a point with which NASA disagreed.
[...]
Boeing and SpaceX have made significant progress during these past eight years, NASA Inspector General Paul Martin and his auditors concluded in Thursday's report.
"However, after more than 2 years of delays both contractors will miss the current schedule to begin crewed test flights in late 2019," they wrote. "Addressing outstanding technical challenges, safety and performance testing, and verification of the contractors' requirements, hazards, and safety concerns likely will take significant time to complete."