NASA Expected to Announce ‘Months-long Delay’ for Crewed Artemis Moon Mission
upstart writes:
NASA expected to announce 'months-long delay' for crewed Artemis moon mission:
NASA leadership is expected on Tuesday to announce a "months-long delay" to the first crewed mission of the agency's flagship Artemis program, according to one current and one former NASA employee.
The delay affects NASA's Artemis II mission, which aims to send four astronauts on a journey to fly by the moon and was slated to lift off this November.
But the mission is no longer expected to take place before 2025, according to the sources, confirming months of speculation that a delay was imminent.
NASA's Inspector General hinted at potential delays for the mission in a November report, citing three main challenges the space agency must address before it can safely fly humans to the moon.
First, the ground structure used to build, transport and launch the program's massive Space Launch System rocket - dubbed Mobile Launcher 1 - "sustained more damage than expected."
The November report stated that repairs to the structure were ongoing.
Second, the heat shield on the Orion spacecraft - intended to be the astronauts' home on Artemis II - "eroded in an unexpected way" during Artemis I as it was exposed to temperatures about half as hot as the surface of the sun upon reentry into Earth's atmosphere.
Finally, the Inspector General noted what NASA officials believed to be "the primary critical path" for the Artemis II mission: preparing Orion for its first crew and integrating it with the European Service Module, which provides power and propulsion. The "critical path" in project planning refers to the aspect of the mission that's expected to take the longest.
Read more of this story at SoylentNews.